Tuesday, 30th Jan 2001 20:11

Town have announced that the terracing units on the new stand are now all in place while work on stabilising the concrete shear walls (an awful lot of work these shear walls aren't they) continues. Blockwork partition wall work is also ongoing. With scaffolding on the roof done, work on the new roof itself can start.

For the three weeks steel roof rafters will be put in place. After this the sheeting panels for the roof can be added while from next week the current Churchman's roof will start to be taken apart.